By Industries
Power Generation Utility Distribution Petroleum Refinement Automotive Manufacturing Pet Food Manufacturing Food Production Manufacturing Beverage Manufacturing Grain Handling & Storage Aerospace Manufacturing Water / Wastewater Treatment / Distribution Railway InfrastructureClient: Westar Energy
Project Date: August 2015 to October 2015
Man Hours: 19,181
Wolf Construction completed the construction of the 100 ft. wide, 500 ft. long, 15 ft. deep water tight tank consisting of 495,000 lbs. of reinforcing steel and 3,400 cubic yards of concrete in 8 weeks, delivering the structure to the owner at design strength ahead of schedule.